• 12 Posts
  • 11 Comments
Joined 1 year ago
cake
Cake day: June 16th, 2023

help-circle





  • I’m really impressed by how quickly the plate is getting assembled. I didn’t expect the manifolds to get added for another week or so, and now they’re at 2 / 3.

    I’m not sure what the bottleneck is at the moment. Once everything is lifted in place they can move B9 over, but they might want to wait until they hit stage adapter is added.

    B9 could go through spin prime tests without the plane being ready, and the plate can get tested without all deluge water & gas tanks present. We’re also it sure how far along the other OLM repairs are (cryo pipes are still being replaced). So there’s a ton of stuff happening in parallel.